Can I Get the Project Schedule Details for Godrej Florenne?

Featured Image of Can I Get the Project Schedule Details for Godrej Florenne?


Yes, the Phase 1 Karnataka RERA filing for Godrej Florenne shares the full project schedule. Work officially began on 15 September 2026, and RERA lists 30 September 2030 as the proposed completion date. The schedule splits construction into sub-structure, super-structure and finishing stages, each with its own start and end date.

Godrej Properties registered Phase 1 under PR/150926/008942, and this phase covers 150 rowhouses on Soukya Road, off Whitefield. The dates sit in a public RERA record, so you can check progress yourself at any time.

Godrej Florenne Key Dates at a Glance


This table puts every key date in one place, so you can plan your money around real dates.

Milestone Date
Building plan approval 28 August 2026
RERA approval (Phase 1 and Phase 2) 15 September 2026
Project start date (as per RERA) 15 September 2026
Expression of Interest opened 15 September 2026
Official launch 20 September 2026
RCC frame work ends 22 February 2029
Proposed completion (RERA, Phase 1) 30 September 2030
Possession quoted by developer (Phase 1) 8 October 2030
Possession quoted by developer (Phase 2) 8 October 2031

Stage 1: Sub-Structure Work Schedule


The sub-structure stage covers everything below the ground floor, from site levelling to the plinth. These works run for about two years, since the 150 homes sit in nine separate blocks.

Work Item Estimated Start Estimated End
Earthwork and levelling 15 September 2026 26 August 2028
Foundation footing work 15 October 2026 25 September 2028
Work up to plinth level 14 November 2026 25 October 2028
Sub-structure flooring 15 October 2026 25 September 2028
Retaining wall Not applicable Not applicable

The long window does not mean slow work on every block. Foundations can start on the first blocks while earthwork goes on elsewhere, so stages overlap.

Stage 2: Super-Structure Work Schedule


Once the plinth is ready, each rowhouse rises to its full G+3 height of about 13.35 metres. This stage brings the frame, walls, plaster, doors, windows and basic services into every home.

Work Item Estimated Start Estimated End
RCC framed structure 14 December 2026 22 February 2029
Masonry construction 14 March 2027 23 May 2029
Plastering (inside, outside and ceiling) 13 April 2027 7 July 2029
Railing and grill fixing 28 May 2027 5 September 2029
Flooring, dadoing, skirting and tiles 12 June 2027 4 November 2029
Doors, windows and ventilators 12 July 2027 3 January 2030
Basic water supply, sanitary and electrical work 11 August 2027 2 February 2030

Stage 3: Finishing Works Schedule


Finishing work gives your home its final look, and it also covers the open areas around it. The last item on the list ends on 30 September 2030, which matches the proposed completion date.

Work Item Estimated Start Estimated End
Weatherproofing (tile and concrete) 10 September 2027 2 February 2030
Elevation work 12 June 2027 3 April 2030
Electrical, water and sanitary finishing 9 November 2027 2 February 2030
Painting 9 December 2027 3 April 2030
Internal and external works, including garden areas 12 July 2027 30 September 2030

RERA marks wardrobes, showcases, kitchen cabinets and puja units as not part of this phase. So you should plan and budget for these items yourself after handover.

How the Schedule Links to Your Payments


Godrej Florenne follows a construction-linked payment plan, so your payments move in step with the schedule above. You pay 10% when the developer allots your unit and another 10% when you sign the agreement.

You pay the rest as the site reaches set stages, such as plinth, slab and finishing work. This structure protects you, because you pay only after work reaches each agreed stage on the ground.

How You Can Track Construction Progress


You do not need to rely only on sales updates to see how the project is moving. Search PR/150926/008942 on the Karnataka RERA portal to read the quarterly progress reports the developer files.

  • Compare each quarterly report with the stage dates in the tables above.
  • Ask the sales team for dated site photos during every payment demand.
  • Visit Soukya Road in person once the RCC frame work starts in December 2026.
  • Check that each demand letter matches a stage the site has actually reached.

To see how these stages fit into the full 20-acre layout, visit the Godrej Florenne master plan page.

FAQs


1. When did construction start at Godrej Florenne?

RERA records 15 September 2026 as the official start date for Phase 1. Earthwork and levelling began that day, and foundation work follows from 15 October 2026 across the site.

2. What is the RERA completion date for Godrej Florenne Phase 1?

The Phase 1 RERA filing lists 30 September 2030 as the proposed completion date. The developer quotes 8 October 2030 as the Phase 1 possession date, just a week later.

3. When will Godrej Florenne Phase 2 be ready?

Godrej Properties has quoted 8 October 2031 as the possession date for Phase 2. You can check the detailed Phase 2 schedule on the Karnataka RERA portal under PR/150926/008943.

4. How long will the RCC structure take to finish?

The RCC frame work runs from 14 December 2026 to 22 February 2029 across all nine blocks. After that, the schedule moves mainly into masonry, services and finishing work until 2030.

5. Does the schedule include interior fit-outs?

No, RERA marks wardrobes, kitchen cabinets, showcases and puja units as not applicable for Phase 1. You will need to plan these fittings yourself once you receive possession of your rowhouse.

6. Where can I verify the Godrej Florenne construction timeline?

Visit the Karnataka RERA website and search for registration number PR/150926/008942. The project page shows the full schedule, approvals and quarterly progress updates that the developer files during construction.